Backfilling means the process used refilling soil (or) sand an excavated area, backfilling quantity usually calculating in m³ (Cubic meter), basically There are two type of backfilling method used in construction work.
1.Handmade Backfilling – The Soil is refilling by Humans.
2. Machinery made Backfilling – The Soil is refilling machinery.

For Example:–
Size of Footing
Length (L) – 3.00 m,
Width (B) – 2.50 m,
Thickness /Depth (D) -0.75 m
Size of Column
Length (L) – 0.50 m
Width (B) – 0.50 m
Thickness /Depth (D) – 3.00 m
Size of PCC
Length (L) – 3.20 m,
Width (B) – 2.70 m,
Thickness /Depth (D) -0.10 m
So, Volume of Backfilling is,
Formula = Total Volume of Excavation Area – (Total Volume of PCC + Total Volume of Footing + Total Volume of Column) +10% of total Backfilling Quantity
What is 10% – While doing backfilling compaction need 10% of More Soil for backfilling, so 10% of total Quantity need to add in calculation for backfilling quantity.
Volume of Excavation = (3.20 +0.6+0.6) X (2.70+0.6+0.6) X (0.1+0.75+3.0) = 66.07 m³
Total Volume of Excavation = 66.07 m³
Volume of PCC – Length X Width X Depth = 3.20 X 2.70 X 0.10 = 0.864 m³
Volume of Footing – Length X Width X Depth = 3.00 X 2.50 X 0.75 = 5.625 m³
Volume of Column – Length X Width X Depth = 0.50 X 0.50 X 3.00 = 0.75 m³
So, Total Volume of back filling is = (66.70 – (0.864+ 5.625+0.75)) + 10%
= (66.07-7.329) + 10%
= 58.831 + 10% of Total Back Filling Area
= 58.831 + (58.831 X 10%)
= 64.71 m³ Total Quantity of Soil (or) Sand required For Backfilling
So, TOTAL VOLUME OF BACK FILLING IS = 64.71 m³
4 comments
Abreeth
Good Explanation , Easy to understand
Dillip Kumar Nanda
20% of addition to be done in case of loose soil and 50% of addition or subtraction to be done in case of disintegrated rock.
Evans Makungo
Great approach.
provy
good work, ladies and gents keep level up.
yours is easy to understand.
keep achieving more.